Today, on 24/10/2025 at 4:04 PM, the site charging of OM Oil and Flour Mills Ltd, Unit-2 was successfully carried out. The commissioning and energization of the electrical substation 33/.433KV were completed in the presence of SDO Mr. Basudev Panda BED, JEE BED Mr.Surya Prakash Behera, Sailashree Bihar Bhubaneswar, Division, representatives from OM Oil and Flour Mills Ltd, Mr.Manoranjan Nayak, Mr.Chandravanu Baral, Mr.Mrutyunjay Rout & Mr.Rajaram (Metering Unit) and the UPM Engineering Pvt. Ltd. (Contractor) team, Mr. Chittaranajan Samal, Mr.Rajat Mahakul, Mr.Debadutta Mahakul, Mr.Rajib Mahakul, Mr.Dillip Majhi, & Mr.Subash Behera.
The charging process included the successful energization of HT panels, transformers, LT panels, and associated distribution systems after completing all pre-commissioning tests and safety inspections. All parameters were verified, and the system was found to be operating smoothly under healthy conditions.
- 33KV HT PANEL VALUE: 33.1KV R Phase, 33.12KV Y Phase, 32.92KV B Phase
- LT PANEL VOLATEGE: R Phase 412.4V, Y Phase 412.1V, B Phase 410.8V

+91 8342000040